Karachi may suffer from severe water crisis, says Report

Karachi may suffer from severe water crisis, says Report

Karachi may suffer from severe water crisis, says Report

Karachi water supply

Advertisement

A recent report has revealed that there are grey chances for Karachiites to have a sufficient quantity of water in the coming two-three years as a major water supply project for the metropolis has been shelved for a few more years.

According to the report, in July 2016, the Karachi Water and Sewerage Board (KWSB) had assigned the construction work for phase one of K-IV to the Frontier Works Organisation (FWO).

According to estimates, completion of the first phase will provide Karachi with an additional 260 million gallons of water per day and will spread across 120 canals and a network of pipelines.

The design and alignments of the project had to be changed again and again for unexplainable reasons. The project has been delayed for the last many years.

It was the responsibility of the water board to provide land and electricity for the project, but it failed and wasted three years from 2015 to 2018, read the publication, adding that as per the official documents, the completion of the first phase of the ‘Fourth Additional Water Supply Project’ has been delayed till 2023.

Advertisement

Moreover, the Ministry of Water and Power has sent the timeline of the project to the Ministry of Planning and Special Initiatives and after three months of approval of the Executive Committee of the National Economic Council (ECNEC), a consultant will be appointed by April this year.

Work on the K-IV project is likely to start by November 2021, as the consultant will then submit the project design, PC-I, and bidding documents by July next year.

The official documents suggested that the Water and Power Development Authority has to complete the civil work of the project in 20 months, by July 2023.

K-IV has already been shelved for about 18 years and civil work of the project has also been stalled since August 2018.

K-IV water project is a municipal infrastructure project being jointly developed by the provincial and federal governments in Karachi, Pakistan, to augment the city’s daily water supply.

The estimated cost is approximately Rs.25.5 billion, while the project is designed to provide 650 million gallons of water daily to Karachi in three phases.

Advertisement

The new water supply will be extracted from Keenjhar Lake through three water canals. The project is slated for completion in mid-2019. K-IV water project is part of Karachi Bulk Water Supply Project.

Advertisement
Advertisement
Read More News On